Jul. 2025 - Reconstruction of the Hawthorn Parkway Bridge was completed ahead of schedule in July of 2025. The parkway and all-purpose trail are now fully open for use.
This project included demolition of the existing Hawthorn Bridge and installation of a new bridge. This included placement of new foundations, sub and superstructures, railings, approach pavements, and utilities, as well as grading, grade stabilization, restoration, and traffic control. The bridge is located in the South Chagrin Reservation on Hawthorn Parkway over the OmniTRAX railroad line in Solon.
Project Type: Reservation Capital Project
Project Phase: Completed
Opening Date: July 11, 2025
Contact: Seth Keller, Project Manager, 216-678-2651 or [email protected]
Project Size: 5,570 sq. ft.
Contracting Partner(s): The Great Lakes Construction Co.
Consulting Partner(s): Euthenics Inc.
Funding: